ABM Building Design Bray Project
Introduction
Avondale Landscapes partnered with ABM Construction to convert a greenfield site in Bray, Co. Wicklow, into a durable football pitch. The project involved stripping and regrading the site, importing 170m³ of topsoil, and laser-grading before seeding with a sports rye grass mix.
Despite challenges from a congested location and one of Ireland’s wettest summers, the team seized a brief weather break in September, working extended hours to complete the pitch on time, ready for regular use.
Location
Client
ARCHITECT
Key Features
Grading Soil
Community Benefit
Challenging Weather
Completed on Time
Key Metrics
stripping
Imported topsoil, laser grade, seed with sports rye grass mix
Strip and regrade existing sub soil
Avondale Landscapes was contracted by ABM Construction to deliver a full redevelopment of an underperforming green area into a high-standard football pitch in Bray, Co. Wicklow. The project required a multi-phase approach, overcoming significant challenges in logistics, soil quality, and adverse weather conditions to meet the client’s specifications.
The project began with the removal and stockpiling of existing topsoil, which covered 7,725m². A cut-and-fill operation followed, where up to 1.2 meters of soil was reduced in half the area to extend the pitch. The subsoil was regraded and adjusted to the desired falls and design, including the removal of existing berms and adjustments to manholes.
Due to poor soil quality and insufficient depth, 170m³ of high-quality topsoil was imported to meet the project’s requirements. Laser grading ensured a precise finish to create an even playing surface.
As the site lacked a drainage system, the subsoil was ripped to a depth of 750mm to break compaction and allow water to percolate effectively, preventing pooling and stagnation. This step was critical to ensuring the long-term usability of the pitch, particularly in wet conditions.
The seedbed was prepared to a fine tilth using harrowing, levelling, and stone-burying techniques. This ensured a smooth, clean surface for the establishment of the sports rye grass mix, chosen for its durability and suitability for heavy use.
Situated in a busy part of Bray, the site presented logistical hurdles. The team had to coordinate material deliveries carefully, maintain road cleanliness with regular sweeping, and manage 500 meters of Harris fencing to secure the site.
Ireland’s summer of 2023 was one of the wettest on record, causing frequent delays and challenges in accessing the site. In September, a narrow weather window allowed the team to complete the final phases, including soil spreading and seeding. The crew’s dedication to extended hours and efficient planning ensured the project stayed on track despite these conditions.
The project was completed within three months, aligning with ABM Construction’s timeline. The result is a robust, well-graded football pitch with excellent drainage and a durable rye grass surface, ready to host regular matches.
This project highlighted Avondale Landscapes’ ability to deliver under challenging conditions, from complex logistics to weather disruptions, showcasing their expertise in sports ground preparation and landscaping excellence.