Case Study – Myrtle Square Dun Laoghaire

Reference: – Patrick O’Reilly, Project Manager (poreilly@cumnor.ie)

Introduction

Avondale Landscapes was awarded the contract for the Myrtle Square & Convent Lane Greening project by Cumnor Construction. This case study outlines the project details, highlighting the challenges encountered, strategies employed, and the successful outcomes achieved by Avondale Landscapes in greening these urban spaces under the guidance and collaboration with Cumnor Construction and DLR.

Duration

Completion of the project took six months; we were not continuously on-site due to the main contractor’s timeline. This was then followed with a 3-year maintenance schedule.

CLIENT

Cumnor Construction

Location

Dún Laoghaire Dublin 18

Landscape Architect

DLR Parks and Landscape Services

Key Features

N

Bio-Retention tree pits

N

Geocellular tree pits

N

Structural soil

N

Transport logistics of 8 large specimen trees

N

Bark Mulch

N

Chestnut Fencing

N

Linear Paving planting

Key Stats

Bulbs planted

Shrubs, grasses, ferns, and herbaceous plants.

specimen trees

mature trees, height 6-8m

Project Challenges

Coordinating the delivery of trees to be lifted in place with cranes. We worked alongside subcontractors to align schedules and tasks to avoid any delays. Due to the time of the year on this project, i.e. Summertime, we had to keep the mature trees watered to prevent dehydration and ensure their establishment.
Pedestrian traffic in a tight space presented a challenge that required careful planning to ensure safety and minimise disruption to both pedestrians and construction activities. We had to sort our shrubs while being mindful of pedestrian traffic along with good housekeeping and good safety behaviours.