Case Study – St. Patrick’s Cathedral, Dublin

Introduction

Our contract with Clancy Construction involved restoring the compound area of St. Patrick’s Cathedral in Dublin to its original condition with reference from old photographs. This required the removal of stone and the importation of topsoil. We removed 270 c

Duration

Completion of the project took two months; we were not continuously on-site due to the main contractor’s timeline.

CLIENT

Clancy Construction

Location

St Patrick’s Cathedral, Co. Dublin

Key Features

N

Compact

N

PROJECT completed ON time

N

Grass seeding

N

Box hedging

Key Stats

Muck away

Imported of enrich topsoil

Project Challenges

The major challenge was the removal of 100 to 150mm of stone from the site with restricted access. Our strategy involved bagging the stone on site, removing the bags by hoisting with a tower crane out of the compound and then transferring them into trucks in St. Patrick’s Park. This was a challenge as we could only transfer the bags onto trucks in St. Patrick’s Park during morning hours.

We then had to remove the membrane carefully and reposition the soil, taking care not to disturb the area due to the presence of historical remains and artifacts. This required careful execution particularly when spreading the enriched soil and levelling the area. It was important to preserve the historical integrity.

While reshaping the landscape to its original contours required careful planning and execution it was imperative not to disrupt the ongoing site activities. We liaised with the Project Manager to navigate the logistics and conservation challenges of the project and thus completing the task to the highest and safest manner possible.