Case Study – Myrtle Square Dun Laoghaire
Reference: – Patrick O’Reilly, Project Manager (poreilly@cumnor.ie)
Introduction
Avondale Landscapes was awarded the contract for the Myrtle Square & Convent Lane Greening project by Cumnor Construction. This case study outlines the project details, highlighting the challenges encountered, strategies employed, and the successful outcomes achieved by Avondale Landscapes in greening these urban spaces under the guidance and collaboration with Cumnor Construction and DLR.
Duration
Completion of the project took six months; we were not continuously on-site due to the main contractor’s timeline. This was then followed with a 3-year maintenance schedule.
CLIENT
Cumnor Construction
Location
Dún Laoghaire Dublin 18
Landscape Architect
DLR Parks and Landscape Services
Key Features
Bio-Retention tree pits
Geocellular tree pits
Structural soil
Transport logistics of 8 large specimen trees
Bark Mulch
Chestnut Fencing
Linear Paving planting
Key Stats
Bulbs planted
Shrubs, grasses, ferns, and herbaceous plants.
specimen trees
mature trees, height 6-8m
Project Challenges
Coordinating the delivery of trees to be lifted in place with cranes. We worked alongside subcontractors to align schedules and tasks to avoid any delays. Due to the time of the year on this project, i.e. Summertime, we had to keep the mature trees watered to prevent dehydration and ensure their establishment.
Pedestrian traffic in a tight space presented a challenge that required careful planning to ensure safety and minimise disruption to both pedestrians and construction activities. We had to sort our shrubs while being mindful of pedestrian traffic along with good housekeeping and good safety behaviours.